I just wanted to say thank you to all the MSI staff who participated in repairing the Surgey Air Handler at Winter Park last evening. The team worked very hard to get all the repairs made during our short window of time in order to keep Surgery from having any humidity issues. Charles did an excellent job of coordinating the work and Steve was a great help in determining what needed to be done in order to repair the unit. I don't know the names of the other guys but I do know they all worked together to get this done in the shortest amount of time possible.
Marcia Gabriel
Construction Coordinator, CGC
~ Florida Hospital
|
Case Study - Northrop Grumman Mechanical Room and Laser Lab
|
Type of Work:
|
Tenant Improvement
|
|
Location: |
2787 S. Orange Blossom Trail
Apopka, FL
|
|
General Contractor: |
Gettysburg Commercial
Dale Hodges
2548 N. Orange Blossom Trail, Suite 800
Orlando, FL 32804
|
|
Project Description: |
MSI’s scope of work includes construction of a new
Class 10,000 Clean Room including air handling
systems, duct work, controls and high efficiency
filtration along with a 550-ton expansion of the
factory’s Central Cooling Plant
|
|
Project Manager: |
Don Baty
|
|
Year of Construction: |
2008-2009 |
|